Barbashela Creek Sewer Replacement Project Begins October 24

print
Dekalb County

Expected to last approximately 14 months (October 2022 to December 2023), barring any weather delays

 

Efforts to improve the watershed system throughout DeKalb County continues on Monday, October 24, with the launch of the Barbashela Creek Sewer Replacement Project. Crews will work towards a wastewater treatment gravity sewer project to rehabilitate the system.

The sewer replacement project is expected to last approximately 14 months (October 2022 to December 2023), barring any weather delays.

Normal construction hours will be from 8 a.m. to 5 p.m., Monday through Friday, excluding major holidays. An increase in construction-related noise and traffic during work hours should be expected.

To learn more about the Barbashela Creek Sewer Replacement Project, join the virtual community meeting on Tuesday, October 18 at 6:30 p.m. via Zoom at: https://dekalbcountyga.zoom.us/j/5029881429

Information also can be obtained by calling the DWM Project Information Line at 1-800-986-1108 or emailing projectinfo@dekalbcountyga.gov with questions.