Thompson Mill Water Main Replacement Project
The Thompson Mill Water Main Replacement Project has been designed to improve the watershed system in Decatur, Georgia. Impacted Stakeholders can learn about the project below.
Project Start Date: May 2023
Timeframe: 22 months from start to finish
Notification Letter: Oct. 19, 2023
Trench Excavation Notification
Service Interruption Notification
Project Update: April 22, 2025
PROJECT COMPLETED: 7.11.25 SL
DeKalb County Engineering and Construction Management hosted two virtual meetings for the Thompson Mill Water Main Replacement Project.
Residents and business owners impacted by the project had the opportunity to learn about how the project will impact service delivery, traffic, and community schedules. See below:
As part of DeKalb County’s $2.4 billion capital improvement program, the Department of Watershed Management (DWM) will be improving the capacity and service of the Watershed systems in DeKalb County. See here:
DeKalb County Press Release for the Thompson Mill Water Main Replacement Project