The Emerald Castle Sewer Upsizing Project will replace 1500 linear feet of aging sewer lines with new 12” ductile-iron pipes. The line repair project is expected to last approximately 4 months (July to November 2022), barring any weather delays. Impacted Stakeholders can learn about the project below. |
Resident Letters | Community Invitation | Press Release | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Start Date: July 6, 2022 Timeframe: 4 months from start to finish. |
What to expect from this project. DeKalb County Engineering and Construction Management hosted a virtual meeting for Emerald Castle Sewer Upsizing Project. Residents and business owners impacted were able to learn about how the project will impact service delivery, traffic, and community schedules. |
As part of DeKalb County’s $2.4 billion capital improvement program, the Department of Watershed Management (DWM) will be improving the capacity and service of the Watershed systems in DeKalb County. See the DeKalb County Press Release for Emerald Castle Sewer Upsizing Project.
|